IJPAM: Volume 110, No. 3 (2016)

Title

A NEW APPROACH IN CRASHING AND
INTRODUCTION OF $P$ FACTOR

Authors

Kanika Mandal$^1$, Kajla Basu$^2$
$^{1,2}$Department of Mathematics
NIT Durgapur
West Bengal, 713209, INDIA

Abstract

Crashing a project means crashing a number of activities to reduce the duration of the project below its normal time. To avoid unfavorable circumstances or to be in competition with other competitors who are to launch same type of products, Crashing is helpful. Because of the uncertainties in daily life, the time duration or the cost involved for the activities in a network can not be known in a precise manner. To deal with the vagueness or imprecise data, it is required to use fuzzy time and cost for activities in a network. A new approach for crashing the project with fuzzy activity times and cost is introduced in this paper. A study has been carried out to improve the probability of achieving the target time. In doing so a new probability factor called p factor has been introduced in the paper for the first time. This p factor will also help the decision maker to choose his own target time. The new approach is efficient and easy to implement for a real life situation. The approach has been discussed step by step theoretically and finally presented with a numerical example.

History

Received: May 12, 2016
Revised: July 25, 2016
Published: November 5, 2016

AMS Classification, Key Words

AMS Subject Classification: 90B99, 90B50
Key Words and Phrases: fuzzy critical pathm crashing, probability factor

Download Section

Download paper from here.
You will need Adobe Acrobat reader. For more information and free download of the reader, see the Adobe Acrobat website.

Bibliography

1
S.Suresh Babu, Y.L.P. Thorani and N.Ravi Shankar, Ranking Generalized Fuzzy Numbers using centroid of centroids, International Journal of Fuzzy Logic Systems, 2 (2012), 17-32, doi: https://doi.org/10.5121/ijfls.2012.2302.

2
N Ravi Shankar, V Sireesha and P Phani Bushan Rao, An Analytical Method for Finding Critical Path in a Fuzzy Project Network, Int. J. Contemp. Math. Sciences, 20 (2010), 953-962.

3
Shih-Pin Chen and Yi-Ju Hsueh, A simple approach to fuzzy critical path analysis in project networks, Applied Mathematical Modelling, 32 (2008), 1289-–1297, doi: https://doi.org/10.1016/j.apm.2007.04.009.

4
Stefan Chanas and Pawel Zielinski, Critical path analysis in the network with fuzzy activity times, Fuzzy Sets and Systems, 122 (2001), 195-204, doi: https://doi.org/10.1016/S0165-0114(00)00076-2.

5
Ahmed Farouk Abdul Moneim,Expected Delays in Completing Projects under Uncertainty, Jordan Journal of Mechanical and Industrial Engineering, 2 (2008), 65-69.

6
Stephan Foldes and François Soumis, PERT and crashing revisited: Mathematical generalizations,European Journal of Operational Research, 64 (1993), 286–-294, doi: https://doi.org/10.1016/0377-2217(93)90183-N.

7
Ten Wei Peng, Mustafa bin Mamat and Yosza bin Dasril, An Improvement of Numerical Result of Crashing CPM/PERT Network, Journal of Science and Technology, 2 (2010), 17-32.

8
I.M. Premachandra, A Goal‐programming Model for Activity Crashing in Project Networks, Journal of Science and Technology, 13 (1993), 79-85.

9
Y. A. Ghaleb and M. M Adnan, Crashing PERT network using mathematical programming, International Journal of Project Management, 19 (2001), 181-188, doi: https://doi.org/10.1016/S0263-7863(99)00061-7.

10
Gary Mitchell and Ted Klastorin, An effective methodology for the stochastic project compression problem, IIE Transactions, 39, (2007), 957-969, doi: https://doi.org/10.1080/07408170701315347.

11
Mustafa bin Mamat, Ten Wei Peng, Yosza bin dasril and Ismail bin Mohd, Multi-Dimensional Nonlinear Knapsack Problem for crashing CPM/PERT, World Applied Sciences Journal, 13 (2011), 341-346.

12
A. Nagoor Gani, A New Operation on Triangular Fuzzy Number for Solving Fuzzy Linear Programming Problem, Applied Mathematical Sciences, 11, (2012), 525-532.

13
Priti Singh, Florentin Smarandache, Dipti Chauhan and Amit Bhaghel, A unit based crashing pert network for optimization of software project cost, Int. J. Contemp. Math. Sciences, doi: https://doi.org/10.1.1.310.187.

14
Ajiboye Sule Adegoke, Measuring Process Effectiveness Using Cpm/Pert, International Journal of Business and Management, 6 (2011), doi: https://doi.org/10.5539/ijbm.v6n6p286.

15
Komesh Sahu and Meenu Sahu, Cost & time and also minimum project duration using alternative method, International Review of Applied Engineering Research, 4 (2014), 403-412.

16
P.K. Suri and Bharat Bhushan, Simulator for Optimization of Software Project Cost and Schedule, cost, risk, and quality criteria, Applied Mathematical Sciences, 4 (2008), 1030-1035.

How to Cite?

DOI: 10.12732/ijpam.v110i3.3 How to cite this paper?

Source:
International Journal of Pure and Applied Mathematics
ISSN printed version: 1311-8080
ISSN on-line version: 1314-3395
Year: 2016
Volume: 110
Issue: 3
Pages: 413 - 426


$P$ FACTOR%22&as_occt=any&as_epq=&as_oq=&as_eq=&as_publication=&as_ylo=&as_yhi=&as_sdtAAP=1&as_sdtp=1" title="Click to search Google Scholar for this entry" rel="nofollow">Google Scholar; DOI (International DOI Foundation); WorldCAT.

CC BY This work is licensed under the Creative Commons Attribution International License (CC BY).